Two kit types use two limited work areas. One type earns more priority points per kit, but it also uses more of a constrained activity. Choosing only the highest points per item can miss the best combination. Optimisation makes both the objective and the restrictions explicit.

Use engineering measurement and design methods for evidence, requirements and comparisons. This chapter introduces its own rates, count balances and inequalities. All operations, times, outputs and scores are original constructed cases; no reported business or personnel performance is implied.

Back to the chapter

After reading, you can

Formulate a small resource-allocation problem and distinguish a feasible solution, a model optimum and an executable whole-unit plan.

01

Translate the decision into quantities with units

Let x be the number of type X kits and y the number of type Y kits in a planning period. In our original classroom model, X uses 2 hours in area A and 1 in B; Y uses 1 in A and 2 in B. Each area has 8 available hours. Constraints are 2x+y≤8 and x+2y≤8, with nonnegative x and y. Both sides of each resource inequality are hours.

Suppose the declared objective is to maximise 3x+4y priority points. These invented points encode a chosen preference, not revenue or a universal social value. The feasible region is the set satisfying every constraint. A preferred but infeasible combination is not an eligible solution. Demand limits, compatibility, quality and human requirements would need additional representation if they govern the actual decision.

02

A continuous solution is a useful bound

First allow fractional quantities as a mathematical relaxation. The feasible polygon has vertices(0, 0),(4, 0),(8/3, 8/3),(0, 4). Their scores are 0, 12, 56/3 and 16. A linear objective on this bounded polygon attains a maximum at a vertex, so the intersection gives about 18.67 points in the continuous model. Both resource constraints are active there.

If kits must be whole, 8/3 of each is not an executable plan. Enumerate integer x from 0 through 4. The largest feasible y values are 4, 3, 3, 2, 0, giving scores 16, 15, 18, 17, 12. Since the coefficient of y is positive, a smaller y for each fixed x cannot improve its score. The best whole-unit pair is therefore x=2,y=3, score 18.

Feasibility and an objective define different parts of optimisationThe original feasible region obeys 2x+y≤8 and x+2y≤8 with nonnegative quantities. Its continuous optimum for 3x+4y is at 8/3, 8/3; the best whole-unit pair is 2, 3.Original allocation model · x and y count kit types0011223344xySolid: 2x+y=8 | Dashed:x+2y=8Circle: continuous optimum | Triangle: best integer pair
Feasible polygon vertices(0, 0),(4, 0),(8/3, 8/3),(0, 4). Objective 3x+4y at continuous intersection is 56/3≈18.67 points. With whole nonnegative counts, best pair(2, 3) gives 18; resource usage 7 and 8 hours. Solid/dashed lines and circle/triangle distinguish the quantities beyond colour.
03

Optimal means best under this model

The integer plan uses 2×2+3=7 hours in A and 2+2×3=8 in B. One hour remains in A, but B is full. Unused capacity in one resource can coexist with a model optimum. Forcing all resources to appear fully occupied is a different objective and can require infeasible or unnecessary work.

Changing the objective, available hours or requirements can change the best plan. A priority score can conceal fairness or service obligations if they are omitted; one solution should not make them disappear. Check the formulation, input uncertainty and implementation conditions independently. A solver can return a precise optimum to a poorly posed question just as a hand calculation can.

Test a tempting high-output proposal

At x=3,y=3, the score would be 21, but each area would require 9 hours. It violates both 8-hour limits, so the larger score cannot make it acceptable. At x=2,y=3, score 18 is feasible with resource totals 7 and 8.

Rounding the continuous solution to x=3,y=3 creates the infeasible proposal. Rounding is not a general integer-optimisation method. Enumeration here is small enough to verify every possible x; a larger model needs an appropriate method and checks rather than simply rounding each output.

Try the reasoning

  1. What makes a plan feasible?

    Show the answer and reasoning

    It satisfies every stated constraint, including resource bounds, nonnegativity and any whole-unit requirement.

  2. Why can one resource have an unused hour at the best integer plan?

    Show the answer and reasoning

    The other resource and whole-unit restrictions prevent adding a beneficial kit within all constraints.

  3. Does optimality establish that the priority points are the right objective?

    Show the answer and reasoning

    No. Choosing and justifying the objective is a separate design and stakeholder decision.

What to carry forward

An optimum is conditional on the objective, constraints and variable definitions; verify that the resulting plan can be implemented.

References

Teaching resources and research supporting this lesson’s explanations and examples.

  1. Process Capacity: Evaluation and OptimizationGurvich · Cornell University teaching resourceCourse notes · PDFcpb-us-e1.wpmucdn.comRead source
  2. Tutorial 1: Introduction to LP Formulations · Spring 2013MIT OpenCourseWare · 15.053Course notes · PDFocw.mit.eduRead source